Nov 16, 2021

Project updates

Changing the skyline

Share

The skyline is changing! Last week we lifted and placed the main absorber column. At 54m in length and weighing over 800 tonnes, it is the largest piece of equipment at our site. The successful lift was executed safely using 3 cranes over several hours.

This milestone comes just two weeks after we placed the precoolers and main cryogenic heat exchanger.

Watch to hear about the planning and teamwork involved to execute this lift safely.