Apr 27, 2021

Project updates

Construction milestone: completion of phase 1 plant piling program

Share

Construction milestone: completion of phase 1 plant piling program
Workers in front of the last pile at the LNG Canada site in Kitimat, B.C.

Last week we drove the last of our Phase 1 Plant Piles. The program began in January 2020 and included 6,483 piles in total.

To celebrate, we made the last pile a special one with custom art recognizing the hard work our of construction team and that of our prime contractor, JGC Fluor (JFJV) and their subcontractor, Soletanche Bachy Canada (SBC).

Construction milestone: completion of phase 1 plant piling program
The last pile of the Phase 1 Plant Piling program at the LNG Canada site in Kitimat, B.C.

You might also like

Environmental Maintenance at Kitimat River Side Channel

Jun 25, 2024

News

Project updates

Environmental Maintenance at Kitimat River Side Channel

The Kitimat River Side Channel project – North & South is complete! Area Construction Managers, Trevor Feduniak and David O’Donnell and Environment Team Lead Rob St. Jean, talk about this complex project.

The view of LNG Canada site construction activities and facilities

Jul 06, 2023

News

Project updates

LNG Canada Project Mid-Year Update Summer 2023

With the project close to 85% complete overall, CEO Jason Klein describes LNG Canada’s progress and the benefits it’s delivering to B.C. and Canada.

Back To Top