Apr 27, 2021

Project updates

Construction milestone: completion of phase 1 plant piling program

Share

Construction milestone: completion of phase 1 plant piling program
Workers in front of the last pile at the LNG Canada site in Kitimat, B.C.

Last week we drove the last of our Phase 1 Plant Piles. The program began in January 2020 and included 6,483 piles in total.

To celebrate, we made the last pile a special one with custom art recognizing the hard work our of construction team and that of our prime contractor, JGC Fluor (JFJV) and their subcontractor, Soletanche Bachy Canada (SBC).

Construction milestone: completion of phase 1 plant piling program
The last pile of the Phase 1 Plant Piling program at the LNG Canada site in Kitimat, B.C.

You might also like

The view of LNG Canada site construction activities and facilities

Jul 06, 2023

News

Project updates

LNG Canada Project Mid-Year Update Summer 2023

With the project close to 85% complete overall, CEO Jason Klein describes LNG Canada’s progress and the benefits it’s delivering to B.C. and Canada.

LNG Canada project construction site, showcasing ongoing progress and infrastructure development.

Jun 16, 2023

News

Project updates

Construction Progress Update, Spring 2023

Watch our construction update to learn more about the ongoing progress on site in Kitimat.

Back To Top