Nov 17, 2022

Project updates

LNG Canada Project Update – Fall 2022

Share

With approximately 3,400 on-site workers, we’ve entered the above-ground construction phase. The tank, cooling towers and trestle are moving towards completion by the end of the year and after receiving the occupancy permit, the first group was able to move into the main admin building.

You might also like

The view of LNG Canada site construction activities and facilities

Jul 06, 2023

News

Project updates

LNG Canada Project Mid-Year Update Summer 2023

With the project close to 85% complete overall, CEO Jason Klein describes LNG Canada’s progress and the benefits it’s delivering to B.C. and Canada.

LNG Canada project construction site, showcasing ongoing progress and infrastructure development.

Jun 16, 2023

News

Project updates

Construction Progress Update, Spring 2023

Watch our construction update to learn more about the ongoing progress on site in Kitimat.