Sep 17, 2019

Is Canada really handing $42 billion of work to China?

Share

The CEOs of Shell Canada and Petronas Canada – the two major partners in the LNG Canada project – say the claim that the remission of steel tariffs for liquefied natural gas (LNG) projects will result in $42 billion of offshoring is simply not true.

While the LNG modules – also known as liquefaction trains – for the LNG Canada plant in Kitimat will be built in Asian steel yards, that only accounts for a portion of the $17 billion capital cost of the LNG plant in Kitimat.

“The majority of what the overall cost is will be spent in Canada,” said Susannah Pierce, director of corporate affairs for LNG Canada.

Shell Canada CEO Michael Crothers and Petronas Canada CEO Mark Fitzgerald said Canadian steel plants simply don’t have the capacity to build LNG modules on the scale required for a project like LNG Canada.

“We can’t be competitive as an LNG export nation unless we have access to the most effective assembly line for these massive modules. That kind of expertise to build modules of that scale doesn’t exist in Canada. But what we do have in Canada is the ability to put them all together.”

– Shell Canada CEO Michael Crothers

You might also like

Hydro testing of LNG tank

Jul 20, 2023

News

Safety

Achieving a Major LNG Tank Milestone

Watch the preparation and successful completion of our LNG tank hydro testing process, as we prepare to deliver responsibly produced, lower carbon energy to the world.

The view of LNG Canada site construction activities and facilities

Jul 06, 2023

News

Project updates

LNG Canada Project Mid-Year Update Summer 2023

With the project close to 85% complete overall, CEO Jason Klein describes LNG Canada’s progress and the benefits it’s delivering to B.C. and Canada.